Project Filter

Heart of the Valley Wastewater Treatment Plant

Kaukauna, WI

Overview

August Winter & Sons, Inc. installed the plumbing, HVAC, process piping and underground piping for the Heart of the Valley WWTP in Kaukauna. The project consisted of installing Pumps, Blowers, Rectifier, Clarifiers, Boilers, Grit Equipment, Mixers, Bar Screens, Compressors, Air Piping, Process Piping, Toilet Rooms and various HVAC Equipment. 

It was necessary to keep the existing WWTP fully operational during the addition and plant modifications and discharge clean treated effluent. Also, this project site was extremely congested and work needed to be planned around existing utilities, bed rock and ground water.

Project included:

  • Fabrication
  • Service and Controls
  • Plumbing
  • HVAC
  • Odor Control
  • Equipment Installation
  • Pipe Fabrication
  • Site Utilities
  • Process Piping
  • Equipment procurement